Quantitative Cost and Schedule Risk Analysis of Nuclear Waste Storage
27 Pages Posted: 3 Jan 2019
Date Written: December 10, 2018
Abstract
This study provides an independent, outside-in estimate of the cost and schedule risks of nuclear waste storage projects. Nuclear waste storage is here defined as special facilities for the wet and dry storage and disposal of high-level (HILW) and low and intermediate-level nuclear waste (LILW). The study analyzed cost and schedule risk profiles of past, completed nuclear waste storage (n = 22), nuclear new builds (n = 194) and underground mining projects (n = 31).
Keywords: nuclear waste storage, nuclear power, cost, schedule, cost overrun, schedule overrun, reference class forecasting, outside view, inside view